The build log

Development Updates

Every Sunday since we fully funded in 2022, we have posted an update to our backers. Here is the whole journey, bundled into quarters. Scroll the chapters, then open any quarter to read every update.

199Weekly updates
17Quarters
41Milestones
Scroll the chapters, tap to expand
The Pulse App Goes LiveQ2 20263 milestones

The Pulse App Goes Live

The team received the Ghydion Pulse source file and put it through weeks of testing, then launched a public interactive demo at ghydion.com/pulse and opened the alpha to all backers, adding hydration-pace and manual tracking. With the patent, trademark, app, and PCB done, they paused weekly updates to plan a capital campaign funding Prototype 2 hardware.

8 updates · Apr to Jun 2026Expand quarterCollapse
From Final CAD To FabricationQ1 20263 milestones

From Final CAD To Fabrication

The team locked the final design, completing the PCB, swapping the side handle for an integrated hand-slip sleeve, and approving the second and final prototype concept. With CAD drawings signed off, fabrication began while the firmware and Pulse app teams started testing communication between them, after which work shifted to letting app development catch up.

13 updates · Jan to Mar 2026Expand quarterCollapse
Mar 29 App Development Continues SteadilyA brief check-in noting app development continued progressing with no specific news, mostly a thank-you to backers. Mar 22 Steady Progress On AppApp testing and refinement for Ghydion Pulse made steady progress, with no concrete details shared in this brief update. Mar 15 Pausing For App To Catch UpThe team paused to let app development catch up, working with the ROK development team to ensure the gallon pairs with the final app version. Mar 8 Fabrication And Firmware Testing BeginFabrication was set to begin shortly while both teams started testing communication between the firmware and app software. Mar 1 Second Prototype Concept ApprovedThe team officially approved the second prototype concept ahead of fabrication, aligning with the MAKO development team on deliverables and next steps. Feb 22 Reviewing Strap And Infusion PodThe development team delivered a backpack-style strap option and fruit infusion POD details for the team to review before approving the updated prototype design. Feb 15 Final CAD Tweaks Before FabricationThe team neared approving final CAD drawings, requesting last refinements to the sleeve and POD inserts, and shared CAD imagery of current progress. Feb 8 Updated Carrying Case Direction CompletedThe development team finished updated prototype prep reflecting the new canvas carrying case, integrated hand-slip concept, and other refinements, with pictures promised next update. Feb 1 Prototype Fabrication Nearing CompletionThe team expected prototype prep CAD specs to review within a week, after which the Mako team would begin fabrication and assembly of prototype parts. Jan 25 Final Sleeve Changes MadeFinal sleeve design changes were confirmed and the team expected updated prototype prep within a week or two before proceeding into fabrication. Jan 18 PCB In Hand, Sleeve PendingThe PCB was officially completed and in hand while the team awaited an updated sleeve sketch with integrated hand slip to finalize prototype prep. Jan 11 Side Handle Dropped For Hand-SlipThe team removed the side handle in favor of an integrated hand-slip on the sleeve, with PCB testing nearly done and app testing targeted for late January. Jan 4 Heading Into Final Prototype FabricationThe team reflected on 2025's design work and announced a final design meeting before moving into fabrication of the second and final prototype.
From Schematic To FabricationQ4 20253 milestones

From Schematic To Fabrication

The team finalized the smart base's screen graphics, then selected the speaker and LED lighting and locked the PCB schematic controlling all electronics. They entered the fabrication phase, ordering parts and prepping the prototype build, and closed the year by sending the completed PCB off for fabrication.

11 updates · Oct to Dec 2025Expand quarterCollapse
Dec 21 PCB Sent Off For FabricationThe completed PCB, the bottle's core electronics, was officially sent off for fabrication as the team wrapped up 2025. Dec 7 PCB Design Nearing CompletionThe PCB design neared completion and housing prototype prep was almost done, setting up the move into fabrication. Nov 30 PCB Entering Next Fabrication PhaseThe PCB advanced toward its next fabrication phase while the team continued wrapping up final prototype preparation. Nov 23 Fabrication Phase Officially BeginsThe development team officially entered the fabrication phase, ordering parts and preparing components for the prototype build. Nov 16 PCB Schematic FinalizedThe team finalized the PCB schematic that controls all the bottle's electronics, clearing the way for prototype prep and PCB fabrication. Nov 9 Speaker And LED Lighting SelectedThe team selected the final speaker and finalized the LED lighting features while continuing to wrap up the PCB and electronics design. Nov 2 Sound System Development BeginsThe team began developing the smart base's sound system and tested speaker options for hydration notifications while finishing the PCB design. Oct 26 Final Stretch Of ElectronicsThe design team continued updating the schematic and PCB based on sound and visual notification changes, projecting completion within about three weeks. Oct 19 Screen Graphics FinalizedWith the screen graphics finalized, the team shifted focus to the sound, lighting, and other electronics ahead of prototype fabrication. Oct 12 Display Solved And Icons DecidedThe team resolved the screen challenges, locked in icon appearance, and refined how the electronics track dehydration. Oct 5 Fine-Tuning Screen GraphicsThe team continued fine-tuning the screen graphics and display design before advancing to the next electronics steps.
Locking The Screen And IconsQ3 20251 milestone

Locking The Screen And Icons

The team finalized a monochrome OLED display with white text and designed the smart base screen graphics and 20x20 pixel icons, advancing the PCB and electronics in parallel. They also iterated on neoprene sleeves and carrying case options and began pursuing approval of a second patent.

13 updates · Jul to Sep 2025Expand quarterCollapse
Sep 28 Screen, Sleeve And App ReviewA development meeting advanced the screen graphics, notifications, sleeve LED visibility, materials, prototype prep, and app progress. Sep 21 Reviewing Screen, Icons And SleeveThe team scheduled a meeting to continue reviewing the screen and finalize the icons and sleeve design. Sep 14 Refining Icons And Carrying CaseThe team spent the week refining the graphic icons, electronics, and carrying case details. Sep 7 Sleeve And Carrying Options ContinueWork on sleeve style and carrying options continued alongside determining electronics and materials for the eventual prototype. Aug 31 Icons And Carrying Case ProgressThe team refined the 20x20 pixel icons and improved the carrying case with added straps and a silicone base for rigidity. Aug 24 Fine-Tuning Screen And SleevesThe team focused on uniform screen icons, neoprene sleeves, carrying options, and tweaks to the visual and audio notifications. Aug 17 Finalizing Graphics And Carrying StrapThe team worked on finalizing screen graphics and the carrying strap design while explaining the deliberate, cost-conscious development pace. Aug 10 Second Patent In ProgressThe team tweaked icon sizes, explored sleeve and carrying options, and began work on approval of a second patent. Aug 3 Smart Base Graphics Near CompletionThe team finalized the visual graphics for the smart base, planning to wrap up PCB and electronics updates once the graphics are approved. Jul 27 Base Screen Images And PCBDevelopers integrated the provided base-screen images and progressed the PCB design while awaiting confirmation on graphics and screen specifics. Jul 20 Monochrome OLED Screen FinalizedThe team finalized a monochrome OLED display with white text and sent off custom screen icons including a water droplet symbol. Jul 13 Monocolor Screen Choice Locked InThe team decided on a monocolor screen with white text on black to avoid production delays and began choosing display images. Jul 6 Screen Testing And Electronics AssessmentMako Design tested the gallon screen and assessed electronics and additional components, reporting mixed progress and challenges during integration.
Trademark, App Demo, And Screen HuntQ2 20252 milestones

Trademark, App Demo, And Screen Hunt

The Ghydion trademark was approved and the team held its first companion app demo, then kicked off a smaller, more portable second prototype. Most of the quarter went into sourcing a color screen, contacting vendors, signing an NDA with a Japanese manufacturer, and ordering samples, while integrating audio and refining the smart base. After briefly choosing a touch screen, the team reversed course to non-touch to protect the timeline.

13 updates · Apr to Jun 2025Expand quarterCollapse
Jun 29 Non-Touch Color Screen ChosenThe team opted for a non-touch color screen to avoid timeline delays and refined the schematic to support it. Jun 22 Touch Screen Selected For PrototypeThe team selected a touch screen for the final prototype, a decision later reversed in favor of non-touch. Jun 15 Reviewing Color Screen OptionsThe team received color screen options meeting size requirements and planned to compare touchscreen and non-touchscreen choices. Jun 8 Sourcing Screen VendorsThe team contacted multiple screen vendors to find a display meeting size, color, and budget requirements. Jun 1 Japanese Color Screen FeedbackThe team reviewed feedback on a color screen sample from a Japanese company and progressed the bottle's audio sound effects. May 25 NDA Sent To Japanese ManufacturerThe team sent an NDA to a promising Japanese screen manufacturer and advanced audio module integration as prototype #2 took shape. May 18 Sound Integration Nearly CompleteThe team nearly finished sound component integration and continued researching a color screen while adjusting the PCB and lighting. May 11 Promising New Color Screen FoundThe team refined the internal CAD and likely found a new color screen, planning to order sample units for testing. May 4 Smart Base And Screen RefinementsThe team refined the smart base for a flat bottom, worked on selecting a color screen, and finalized three customizable buttons. Apr 27 Second Prototype Shrunk For PortabilityThe team made the second prototype more carry-friendly while still a gallon and prepared to sync with Rok Software on the app. Apr 21 App And Prototype ProgressingThe team reported steady progress on app development and the second prototype but shared no detailed updates this week. Apr 13 First App Demo Looks PhenomenalThe team held its first Ghydion app demo, confirmed the trademark approval, and began second prototype development. Apr 6 Trademark Officially ApprovedThe Ghydion trademark was officially approved while the app, bottle, and signature sound effects continued progressing.
Prototype Testing Into Phase TwoQ1 20252 milestones

Prototype Testing Into Phase Two

The team ran trial testing on the first prototype, calibrating water volume and refining handles, straps, sleeves, and pod inserts, then completed its final review and annotated changes for a second version. They signed a phase-two development agreement with Rok Software, advanced the Pulse app with an early dashboard and lockout feature, and filed a second patent for review.

13 updates · Jan to Mar 2025Expand quarterCollapse
Mar 30 Phase Two Planning With PartnersThe team coordinated details and timelines for phase two with development partners Mako and Rok Software. Mar 23 Quiet Week Before Big NewsA brief thank-you note with no major updates as the team counted down to upcoming announcements. Mar 16 Phase 2 Development Agreement SignedThe team signed an agreement with developers to begin the next prototype phase and kicked off another step in app development. Mar 10 App And Prototype 2 Timelines SetRok Software projected app completion by end of April and the second prototype in four months, while a second patent went under review. Mar 2 Early App Dashboard Sneak PeekThe team shared an early version of the app dashboard showing hydration tracking, goal-setting, and planned gamified features. Feb 23 Meetings On Production Prototype Lined UpThe team scheduled meetings to discuss the production prototype revisions from testing and review phase two app progress. Feb 16 App Lockout Feature And Handle DesignThe team worked on the app lockout feature and took notes on prototype handle design, size, weight, straps, and pod inserts. Feb 9 Prototype Updates From First Testing RoundThe development team implemented changes from the first testing round while app development continued progressing. Feb 2 First Prototype Final Review CompletedThe team completed the final review of the first prototype and prepared annotated changes for the second and final version. Jan 26 Next Phase Of Prototype TestingAfter weeks of testing, the team prepared to begin the next testing phase with upgraded handles, sleeve, strap, and pod inserts. Jan 19 Prototype Testing Going WellPrototype testing progressed well and the team shared footage of the prototype in action. Jan 12 Prototype Testing And Press FeaturesTeam testing of the prototype went well and Ghydion was featured in several articles, with app development estimated at two to three months. Jan 5 Trial Testing Of Prototype BeginsTrial testing began, focusing on the bottle's water volume calibration and overall functionality across real-world scenarios.
From Electronics To Working PrototypeQ4 20245 milestones

From Electronics To Working Prototype

MAKO installed the electronics PCBs, integrated the intake sensor and screen, and fully assembled the first working prototype, which arrived in December and entered testing on water calibration, structure, and sensor accuracy. The team diagnosed low-volume sensor dead space, planning a flat bottle bottom for the next iteration, and onboarded an app design team that approved the Pulse app architecture and wireframe.

13 updates · Oct to Dec 2024Expand quarterCollapse
Dec 29 Prototype Testing Officially BeginsThe prototype arrived and testing began on water calibration, environmental performance, bottle structure, and sensor functionality. Dec 22 First Working Prototype ArrivesThe team received the first working prototype and prepared to begin rigorous testing trials before finalizing the design. Dec 15 Prototype Shipped For Team ReviewThe prototype shipped for review, with MAKO's volumetric sensing accurate to about plus or minus one percent except below 500 mL. Dec 8 Volume Refinements For Next PrototypeMAKO progressed on most volume scenarios and chose to solve remaining niche volume challenges in the next prototype iteration. Dec 1 Prototype Testing And Firmware IntegrationPrototype testing continued at MAKO alongside firmware integration to ensure measurement accuracy and performance. Nov 24 Flat Bottom Fix For Sensor AccuracyThe team identified sensor dead space and planned a flat bottle bottom in the next iteration to improve low-volume accuracy. Nov 17 Prototype Finalized For ShipmentThe prototype was finalized and prepared for shipment, with the testing cycle focused on water calibration and software reporting. Nov 10 Prototype Assembled And App Wireframe ApprovedThe prototype was fully assembled with integrated base electronics, and the team approved the Ghydion Pulse app architecture and wireframe. Nov 3 Screen Operational, Electronics WorkingThe screen became operational and electronics ran smoothly as MAKO awaited the assembled unit to finish prototype testing. Oct 27 Sensor Integrated Into Smart BaseMAKO finalized integration of the delicate intake sensor and screen, aiming to complete final prototype assembly the coming Tuesday. Oct 20 MAKO Reviews Prototype AssemblyMAKO continued reviewing the prototype for final assembly and integration, with a returning team member helping them catch up. Oct 13 App Design Team OnboardedThe team met its new app design team and reported that prototype testing was ongoing and progressing positively. Oct 6 Electronics PCBs Installed In PrototypeThe team installed the electronics PCBs into the prototype, though personnel shifts pushed final assembly and testing back a couple of weeks.
Prototype Ships, Pulse App StartsQ3 20242 milestones

Prototype Ships, Pulse App Starts

MAKO finalized the pressure-sensor and main PCBs, then completed and shipped the prototype for functional testing, with firmware and housing integration following. The team kicked off Pulse app development, bringing on ROK Development and defining v1.0 features. Ghydion also earned several press features and a Las Vegas TV appearance.

13 updates · Jul to Sep 2024Expand quarterCollapse
Sep 29 Approaching Prototype Functional TestingThe team expected to finalize the prototype within a week and begin reviewing its functional elements, despite some MAKO team transitions. Sep 22 PCB And Firmware Integration UnderwayMAKO reviewed housing components, completed firmware and programming, and worked to assemble the two PCBs over the next two weeks. Sep 15 Pulse App Developer Talks BeginMAKO neared shipping the prototype back, and the team began planning Pulse app integration with ROK Development for future fitness app support. Sep 8 Featured In New York WeeklyGhydion Co. was featured in New York Weekly while development, testing, and app work continued steadily. Sep 1 Pulse App Version 1.0 Features DiscussedThe founder discussed Pulse App v1.0 features with the new developer, including locking your phone until you meet your hydration goal. Aug 25 Steady Progress In Prototyping PhaseNo major news this week, with the team continuing to refine details during the prototyping phase. Aug 18 Featured On Las Vegas Morning BlendTwo founders appeared on Las Vegas TV's The Morning Blend as prototype testing neared and Pulse App features were being defined. Aug 11 Prototype Complete And Shipping For TestingThe prototype was officially completed and shipped to the team for testing, shifting focus to the Pulse app and production planning. Aug 4 Featured In Two Major PublicationsThe team was featured in two publications and continued app development conversations as prototype arrival neared. Jul 28 Pulse App Development BeginsThe team began Pulse App development and previewed packaging designs while awaiting final PCBs to complete the prototype. Jul 21 Heading To Vegas TV AppearanceMako continued testing and quality review, with a non-electronic prototype version expected around August 5th ahead of a live TV appearance. Jul 14 Finalizing Pressure Sensor PCBThe team focused on finalizing the pressure-sensor PCB electronics, hoping to wrap up within two weeks before sending it to MAKO. Jul 7 Dialing In Electronics AssemblyMako finalized the physical prototype and prepared to test the main PCB while awaiting components for the pressure-sensor PCB.
From Fabrication To First PrototypeQ2 20244 milestones

From Fabrication To First Prototype

The Ghydion Gallon entered fabrication at MAKO, with custom housing parts and the main PCB progressing despite component-sourcing delays that forced one part to be self-soldered. By quarter's end the team had received all physical prototype parts, flagged a smart-base ribbing fix, and neared completion of the second PCB. The official patent certificate also arrived.

13 updates · Apr to Jun 2024Expand quarterCollapse
Jun 30 Second PCB Nears Production EndMAKO pushed on the final prototype sections as the second PCB neared completion, and Ghydion was featured in The Source Magazine. Jun 23 Physical Prototype Parts ReceivedThe team received all physical prototype parts, identified a smart-base ribbing improvement, and awaited PCB confirmation while their TV episode launched. Jun 16 Main PCB Enters FabricationThe main PCB entered fabrication after component-availability challenges, as the team pushed to align prototype completion. Jun 9 Prototype Parts Near CompletionThe custom prototype parts were almost finished and expected to ship within a week, while the PCB needed about two more weeks pending component availability. Jun 2 Team To Self-Solder PCB ComponentA hard-to-source PCB component was procured separately to be soldered in-house, housing parts neared completion, and Ghydion was featured in Disrupt Magazine. May 26 Counting Down To First PrototypeThe Mako team assembled and tested while awaiting a few integrated PCB components, with housing and electronics expected to finish together for final assembly. May 19 PCB And Prototype Fabrication UnderwayPCB and prototype fabrication was underway with initial prototype completion targeted in four to six weeks. May 12 Ghydion Gallon Enters FabricationThe Ghydion Gallon entered fabrication, with custom parts estimated at three to four weeks and the PCB waiting on a few components. May 5 Brief Thanks During FabricationA short gratitude-focused note reported only that the first prototype remained in fabrication. Apr 28 Countdown To First PrototypeA brief update marked the countdown to the first prototype's fabrication and assembly, reflecting on the four-year journey. Apr 21 Patent Certificate ArrivesThe official patent certificate arrived in the mail while the prototype continued in fabrication. Apr 14 A Few Weeks From PrototypeA brief update stated the Ghydion Gallon was in fabrication and just a few weeks from the first prototype. Apr 7 Prototype Fabrication Has BegunThe first prototype was submitted to fabrication at MAKO and was expected ready in three to four weeks, with production targeted for 2024.
From PCB To First PrototypeQ1 20242 milestones

From PCB To First Prototype

Mako Design began physically building the first Ghydion prototype, sizing the bottle, lid, casing, and smart base before turning to the electronics. The team completed the main schematic and finished the PCB design, then began final review ahead of fabrication. Ghydion also hired a PR firm and web developer and landed several press features.

13 updates · Jan to Mar 2024Expand quarterCollapse
Mar 31 Prototype Plan Review UnderwayThe team prepared to meet and review prototype plans, planning to approve them and begin fabrication if favorable. Mar 24 Prototype Prep And Press FeaturePrototype prep continued as parts were prepared and approved, and a feature ran in LA Entertainment Weekly. Mar 17 PCB Design CompleteMAKO Design finished the PCB design, satisfying most of the electrical work, clearing the way for prototype fabrication after final review. Mar 3 Prototype Layout FinalizedThe electronics team finalized the prototype layout details, putting the project about two weeks from a pre-fabrication review. Feb 25 Schematic Done, Layout FinalizingThe electronics team completed the main schematic and was finalizing layout, with prototype fabrication projected within three to four weeks, plus a Hype Magazine feature. Feb 18 Four Weeks From PCB FinalizationThe team reported it was about four weeks from finalizing the PCB design before fabrication, with mechanical and electronic components nearly built. Feb 11 Steady Progress On PrototypeA brief update noted Mako Design's continued progress, putting the project about five weeks from finalizing the PCB and entering fabrication. Feb 4 PR And Web Firms HiredMako advanced CAD and PCB updates on roughly a six-week track while Ghydion hired a PR firm and web developer and noted pre-orders closing soon. Jan 28 PCB Sizing Finalized With Smart BaseMAKO finalized the PCB sizing and orientation with the smart base and progressed on components, estimating prototype completion in six to seven weeks. Jan 21 Prototype On Track For Late FebruaryMako Design reported standard progress building the first prototype, updating the bottle, base, lid, and casing, on track for late February. Jan 14 Prototype Fabrication Begins At MakoMako began physically building the first Ghydion prototype, starting with the base unit dimensions, while the founder filmed The Blox in Tulsa. Jan 7 Prototype Work In Full SwingMako confirmed the housing and base sizing and turned to the PCB schematic, as the founder prepared to represent Ghydion on The Blox. Jan 1 Happy New Year From GhydionA New Year greeting thanking supporters and noting the first prototype was approaching, with no concrete development news.
Breadboard Done, Prototype BeginsQ4 20232 milestones

Breadboard Done, Prototype Begins

Mako finished and tested the breadboard model, refining calibration, volume measurement, firmware, and the screen until all pieces passed. With those results in hand, the project officially entered the prototype phase, and the team signed the prototype development agreement to fund the six-step build from PCB design through testing.

11 updates · Oct to Dec 2023Expand quarterCollapse
Dec 17 Prototype Phase Officially UnderwayThe team announced the prototype phase had begun and laid out the six development steps from PCB design through evaluation and testing. Dec 10 No Major Updates This WeekA brief note that scheduling conflicts delayed the Mako meeting, with no substantive progress to report. Dec 3 Signing The Prototype AgreementThe team prepared to sign the prototype development agreement and fund the next phase, and skipped personalized supporter mailers this year. Nov 19 Planning The Next PhaseThe team met with Mako to solidify plans for the prototype phase amid the holiday slowdown and prepared holiday greetings for pre-order supporters. Nov 12 Officially Entered Prototype PhaseMako finalized the breadboard model with strong test results, and the project officially moved into the prototype phase. Nov 5 Ready To Move To PrototypeMako confirmed the project was ready to enter the prototype phase, with a follow-up call planned to set the timeline. Oct 29 Mako Meeting PostponedA calendar conflict pushed the planned Mako meeting about next steps to the following week, with no new progress reported. Oct 22 Breadboard Testing CompleteThe final breadboard pieces passed testing, clearing the way to move into the PCB model and prototyping phase. Oct 15 Wrapping Up The BreadboardMako neared completion of the breadboard prototype after a small part delay, planning to finalize firmware and volume-measurement calculations. Oct 8 Refining Calibration And VolumeThe team continued refining calibration, volume calculations, and the screen for the breadboard, expecting to enter the prototype phase soon. Oct 1 Fine-Tuning The ElectronicsMako fine-tuned the electronics setup from testing and calibration, aiming to wrap up the breadboard within about two weeks.
Breadboard And Sensor CalibrationQ3 20231 milestone

Breadboard And Sensor Calibration

MAKO Design built and tested the breadboard prototype, confirming Honeywell water sensors responded well to water levels and finalizing the smart base coding, firmware, and volume-calculation algorithm. The team confirmed the December shipping date would slip, projecting the breadboard done by mid-October before a two-to-three-month PCB stage. Ghydion also became a verified veteran-owned business and was selected to compete on the TV show The Blox.

13 updates · Jul to Sep 2023Expand quarterCollapse
Sep 24 Breadboard Wrapping Up Mid-OctoberMako expected to finish the breadboard by mid-October, and the team confirmed the December shipping timeline would be missed. Sep 17 Firmware And Volume Calculations ProgressThe team continued firmware and algorithm work to integrate volume calculations with the bottle's base, reporting steady progress. Sep 10 Smart Base Coding FinalizedMako finalized the smart base coding and algorithm, projecting the breadboard done by mid-October before the two-to-three-month PCB stage. Sep 3 Detailing Sensor CalibrationMako detailed sensor calibration protocols and firmware integration including charging logic and the accelerometer, with a next-steps meeting pending. Aug 27 Progress On Firmware And CalibrationMako advanced programming, firmware, and calibration work, with a meeting planned to discuss the next steps. Aug 20 Firmware For Screen And SensorMako finalized screen firmware and coding for memory, calibration, and sensor-based volume calculation, and planned to reassess the timeline. Aug 13 Sensors Respond Well To Water LevelsTesting showed the Ghydion sensors and breadboard model responded well to water levels, building momentum toward a working prototype. Aug 6 MAKO Progresses On Breadboard PhaseMAKO Design advanced the breadboard phase, calibrating sensors, integrating the base screen with hardware, and reviewing circuit assembly. Jul 30 Water Sensor Testing ContinuesMAKO continued evaluating the water level sensors, with strong initial results, and still needed to test sensor behavior with the lid on versus off. Jul 23 Honeywell Sensors Pass Preliminary TestsHoneywell's water sensors produced strong results in preliminary breadboard testing, though more testing remained before official prototyping. Jul 16 Selected To Compete On The BloxGhydion was chosen from 20,000 applicants to compete on the startup TV show The Blox, with filming set to begin in January. Jul 9 Calibration Continues With Honeywell SensorsThe MAKO team continued testing and calibration while determining the best way forward using the Honeywell sensors. Jul 2 Verified Veteran-Owned BusinessGhydion Co. became a verified veteran-owned business, and the team decided to use Honeywell's existing water-sensing technology.
Breadboard Prototyping And Sensor TestingQ2 20233 milestones

Breadboard Prototyping And Sensor Testing

MAKO entered early prototyping, finalizing the parts list, ordering components, and assembling a breadboard to refine the circuit and volume-sensing design. They brought in Honeywell to implement and calibrate the level and pressure sensors, testing accuracy against water and mixed powders. The one-gallon stainless steel frame arrived for evaluating electrical functions and water-level sensing.

13 updates · Apr to Jun 2023Expand quarterCollapse
Jun 25 Sensor Calibration And Breadboard AssemblyMAKO engineers calibrated and implemented the Honeywell sensors while also assembling the other breadboard components. Jun 18 Testing Sensor Accuracy And Air PressureMAKO continued sensor testing with Honeywell, assessing air pressure changes and the effect of water and mixed powders on measurement accuracy. Jun 11 Honeywell Joins On Sensor ImplementationMAKO began discussions with the Honeywell sensor manufacturer on implementation, and detailed photos were promised the following week. Jun 4 Stainless Steel Frame Arrives For TestingMAKO received the one-gallon stainless steel frame and began evaluating electrical functions and water level sensing on it. May 28 Evaluating Sensor Options For PrototypeThe MAKO team continued evaluating sensor options, estimating about two weeks to obtain and calibrate additional components. May 21 Early Prototype Assembly ProgressesMAKO assembled the early prototype, weighing pressure sensor options while detailing the breadboard electrical components. May 14 Breadboard Assembly BeginsThe MAKO development team began assembling the breadboard model, starting to bring the Ghydion Gallon to life. May 7 Most Breadboard Components DeliveredMost components needed for the breadboard model arrived, with MAKO set to begin assembly once the last few parts came in. Apr 30 Components Inbound, Two Sensors To TestBreadboard components were expected within about a week, and the team planned to test two different level sensors to find the best one. Apr 23 MAKO Orders Breadboard PartsMAKO ordered the parts to begin constructing the breadboard, the first step in prototyping. Apr 16 Finalizing The Breadboard Parts ListMAKO worked to finalize the list of components for the breadboard model, after which they would be cleared to order parts and start assembly. Apr 9 Prototype Breadboard Phase BeginsThe prototype phase began with a breadboard orientation, where designers would compile and test electronics, focusing on the volume sensor. Apr 2 Early Prototype Development UnderwayThe project entered early prototype development, building a breadboard to experiment with and refine the Ghydion Gallon's circuit design.
From Concept To Prototype PhaseQ1 20231 milestone

From Concept To Prototype Phase

The team worked with MAKO Design to finalize the concept sketch and CAD package, focusing on how to accurately track water volume in the smart base. After approving the final concept document, they officially entered the prototype phase and received MAKO's initial prototype proposal. Design changes included a collapsible handle and removed glass windows, and shipping slipped to December 2023.

12 updates · Jan to Mar 2023Expand quarterCollapse
Mar 26 Prototype Proposal Received From MAKOThe team received the initial prototype proposal from MAKO Design, advancing the Ghydion Gallon into prototype construction using the CAD concept. Mar 19 Prototype Phase Officially BeginsThe project officially entered the prototype phase to build a working model and refine details ahead of testing and shipping. Mar 12 Prepping Prototype Phase With MAKOThe team recapped timeline shifts to summer prototyping and winter 2023 shipping, plus design changes to a collapsible handle and removed glass windows. Mar 5 No Major News, Meeting ScheduledNo major updates were shared while the team awaited a next-steps meeting with MAKO scheduled for March 13th. Feb 26 Cleared To Begin Prototype DevelopmentAfter evaluating smart-base attachment and shutter-pod mechanisms with MAKO, the team gained enough direction to move forward with prototype development. Feb 19 Concept Design Still Under ReviewThe team remained in the concept design review and approval process, promising a detailed review update the following week. Feb 12 Final Concept Design Document ReceivedThe team received the final concept design document from MAKO, with prototype phase to begin after review and approval. Feb 5 Concept Sketch Nearing CompletionThe team reported MAKO's progress toward finishing the concept sketch before advancing to the 3D CAD design package. Jan 29 Awaiting Tracking Feature ResearchNo new updates were shared as MAKO researched ways to incorporate the base tracking feature, with a deliverable expected in one to two weeks. Jan 22 Shipping Pushed To December 2023The team announced the ship date moved to December 2023 to allow more research and development on the volume-tracking feature. Jan 15 Timeline Extended To Year EndAfter a technical review with MAKO, the team revised expectations to a prototype by summer and the final product near year end. Jan 8 Gearing Up For Phase TwoThe team and MAKO reviewed all components and focused on developing options to accurately track water volume in the base.
From Components To Concept SketchQ4 20222 milestones

From Components To Concept Sketch

The team finished revising the electronic components document with MAKO Design and advanced into the concept sketch phase, receiving the initial sketch and beginning revisions toward the 3D CAD blueprint. Backers were polled on design features and voted for a collapsible handle, while the team shipped backer duffel bags and attended the Mr. Olympia Expo.

12 updates · Oct to Dec 2022Expand quarterCollapse
Dec 18 Mr. Olympia Expo And Design ChangesThe team attended the Mr. Olympia Expo, began shipping duffel bags, and confirmed MAKO design changes including handle, sleeve, and insulation improvements. Dec 11 Awaiting Revised Concept SketchNo major updates were shared while the team awaited the revised concept sketch from MAKO, expected in one to two weeks. Dec 4 Concept Sketch Revision UnderwayThe team began revising the concept sketch before the 3D CAD blueprint phase and sent the duffel bags back to fix a stitching error. Nov 27 Backers Vote Collapsible HandleBackers voted overwhelmingly for a collapsible handle, and the team prepared to brief MAKO to revise the concept sketch. Nov 20 Handle Style Poll For BackersThe team asked backers to weigh in on their preferred handle option as it worked through modular design features. Nov 13 Blueprint Preview With MAKOThe team previewed the Ghydion Gallon blueprint after meeting with MAKO and planned a Facebook poll to gather feedback on design options. Nov 6 Initial Concept Sketch DeliveredThe team received the initial concept sketch from MAKO and prepared to revise minor details, plus readied duffel bags for shipping. Oct 30 Awaiting Concept Sketch DeliverableNo updates were shared while the team remained in the initial concept sketch phase, with a deliverable expected in one week. Oct 23 Concept Sketch On TrackMAKO Design reported the initial concept sketch was on track with a deliverable expected in about two weeks. Oct 16 Concept Sketch UnderwayMAKO Design indicated the initial concept sketch phase should be completed in about three weeks. Oct 9 Moving Into Concept Sketch PhaseAfter reviewing the electronic components document with MAKO, the project advanced to the initial concept sketch phase with 2D and 3D CAD work. Oct 2 Electronic Components Document RevisionsNo major news, as the team continued making revisions to the electronic components document.
Funded And Electronics Research BeginsQ3 20224 milestones

Funded And Electronics Research Begins

The 45-day campaign closed at over $20,000, funding phase one of design. MAKO Design then kicked off a three-to-four-week electronics research phase, completing the electronic components document and starting versatility revisions. The team also shipped backer thank-you gifts, brought on advisors, and made its first $1,500 charity: water donation.

14 updates · Jul to Sep 2022Expand quarterCollapse
Sep 25 Adding Versatility RevisionsMinor revisions to the electronic components document were underway to make the gallon more versatile and customizable for different users. Sep 18 Electronic Components Document CompleteThe electronic components document was completed and readied for review, all backer mailers shipped, and the website was set to be updated. Sep 12 Awaiting Electronic Component DocumentMAKO Design requested a few more days on the electronic component document, and the last backer mailers were shipping that week. Sep 4 On Track, Mailing Thank You GiftsThe electronics component research phase was due in about a week, and thank you gifts were being mailed to backers. Aug 28 Keeping Strong MomentumThe electronics component research phase remained on track for completion in one to two weeks, with backer thank you gifts shipping the following week. Aug 21 Electronic Research Phase BeginsMAKO Design started the electronic research phase, a three to four week step assessing components and materials before full development. Aug 14 First Charity Water DonationGhydion made its first contribution to charity: water, pledging $1,500 and committing 10% of every gallon sold to the cause. Aug 7 Advisors Join, Licensing Interest GrowsThe team brought on experts and advisors and reported investor interest plus a licensing offer from a major athletic organization. Jul 31 Crowdfund Ends Over $20K RaisedThe 45-day crowdfunding campaign officially ended, raising over $20,000 to fund phase one of product design. Jul 25 Final Campaign WeekThe team recovered from COVID and entered the last week of the campaign before phase one begins. Jul 19 Phase One Two Weeks OutWith phase one two weeks away, the team reaffirmed its pledge to donate over $1,200 to charity: water. Jul 13 Backer Gift And Sponsorship TalksThe team was preparing a backer thank you gift and negotiating sponsorship opportunities with sports industry names ahead of phase one. Jul 8 Featured In Yanko Design MagazineGhydion was featured in an online Yanko Design article with 22 days left in the campaign. Jul 4 Over $16K Raised, Affiliate ProgramThe campaign passed $16,000 raised and launched an affiliate referral program offering commissions for sign-ups.
Fully Funded In One HourQ2 20221 milestone

Fully Funded In One Hour

The Ghydion crowdfunding campaign launched and reached its full funding goal within the first hour. By the end of the first week, backer support had pushed it to 265 percent of the original target.

1 updates · Apr to Jun 2022Expand quarterCollapse
The beginning — Jun 21, 2022. This is where it all started.